June 8, 2017

Monroe Street Construction: Beginning the week of June 12 Monroe Street will be milled and resurfaced between Lincolnway East and Logan Street. The roadway will be opened back up to normal traffic after the pavement is placed. The west-bound lane will be closed after the fair to allow installation of the water main beneath the tracks.

Logan Street Construction: By fair-time, the north end of Logan will be completely closed. Businesses along Logan Street will have the south end of Logan as their only access in and out of the corridor.

US Hwy 33, Main to Madison: Installation of bridge beams begins the week of July 17 at Cottage Avenue and at Lincoln Avenue. While bridge beams are being installed, there will be temporary delays in traffic flow.

Blackport Drive: The City has authorized the addition of 6 new street lights along Blackport Drive between Monroe Street and Lincoln Avenue. These lights should be installed before the fair.

Contact the City of Goshen Engineering Department with questions: 574-534-2201 or engineering@goshencity.com